Analysis Performance for Evaluation of Schedule Irregularities on Bore Pile Foundation with FTA

: A Case Study of Opus Apartment Project in Batam

  • Melvin Melvin Faculty of Civil Engineering and Planning, Universitas Internasional Batam, indonesia
  • Andri Irfan Rifai 1Faculty of Engineering & Planning, University of Internasional Batam
  • Amanatullah Savitri Faculty of Civil Engineering and Planning, Universitas Internasional Batam, indonesia
Keywords: Delay, FTA, Lateness, Project

Abstract

Purpose: In construction projects, delays are disruptive and expensive. Therefore, the reason for the schedule delay needs to be identied. The delay factors determined in previous research were predominantly studied through surveys. In these studies, the participants were a stakeholder in construction projects, and the reason for schedule lateness was identied through their point of view.

Design/methodology/approach: This research is conducted at a bored pile project in Opus Apartment, Batam, Indonesia. The studies are done through the Fault Tree Analysis method to find the root causes of the delay.

Findings: Causes of delay in construction to prevent lateness on future construction projects.

Research limitations/implications: Evaluation of delay causes on the bore pile foundation project in Opus Apartment.

Practical implications: Evaluation of lateness in construction project through Fault Tree Analysis

Paper type: Case Study

Downloads

Download data is not yet available.

References

Abdurrohman, A. (2021). Analysis of Factors Causing The Delay of the Storage Tank Project Using Fault Tree Analysis. IPTEK Journal of Proceedings Series, 6, 563–568.

Alenezi, T. A. (2020). Covid-19 causes of delays on construction projects in Kuwait. IJERGS.

Dingbang Zhang, Hang Zhang, & Tao Cheng. (2020). Causes of Delay in the Construction Projects of Subway Tunnel. Advances in civil engineering. https://doi.org/https://doi.org/10.1155/2020/8883683

Dirgha S. Mahandeka, Silvianita, S., & Rosyid, D. (2015). Fault Tree Analysis for Investigation on the Causes of Project Problems. Procedia Earth and Planetary Science, 14, 213–219. https://doi.org/10.1016/j.proeps.2015.07.104

Gamal, Y. A., & Mostafa Abd Elrazek. (2020). Using the fault tree for analysis the schedule delay factors. IOP Conference Series: Materials Science and Engineering. https://doi.org/10.1088/1757-899X/762/1/012009

Gunduz, M., Nielsen, Y., & Ozdemir, M. (2013). Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey. Journal of Management in Engineering, 29, 133–139. https://doi.org/https://doi.org/10.1061/(asce)me.1943-5479.0000129

H. M. Al-Humaidi, & F. Hadipriono Tan. (2010). A fuzzy logic approach to model delays in construction projects using translational models. Civil Engineering and Environmental Systems, 27(4), 353–364. https://doi.org/https://doi.org/10.1080/10286600903362797

Hsu, P. Y., Aurisicchio, M., & Angeloudis, P. (2017). Investigating schedule deviation in construction projects through root cause analysis. Procedia computer science.

Ibrahim, A. T. (2022). The Effects of Delay and Time Management Building Construction: A Review. International Journal of Scientific Advances, 628–632.

Jonbi, Andreas, A., Arini, R. N., & Yuze, M. (2020). Analysis Of Delay Factors And Construction Claims Of Apartments And Commercial Building. Jurnal Infrastruktur, 6(1), 39-45. https://doi.org/https://doi.org/10.35814/infrastruktur.v6i1.1293

Mohamed Saad Bajjou, & Anas Chafi. (2018). Empirical study of schedule delay in Moroccan construction projects. International Journal of Construction Management, 783–800. https://doi.org/https://doi.org/10.1080/15623599.2018.1484859

Muhadi, M. N., & Yudoko, G. (2021). Root Cause Analysis of Project Delay in BGC-TEG Project. European Journal of Business and Management Research, 6(6), 128–132. https://doi.org/https://doi.org/10.24018/ejbmr.2021.6.6.1161

Muneeswaran, G., Manoharan, P., Awoyera, P., & Adesina, A. (2020). A statistical approach to assess the schedule delays and risks in Indian construction industry. Journal International Journal of Construction Management, 20(5), 450–461. https://doi.org/https://doi.org/10.1080/15623599.2018.1484991

Mustafa Jahangoshai Rezaee, Samuel Yousefi, & Ripon Kumar Chakrabortty. (2019). Analysing causal relationships between delay factors in construction projects A case study of Iran. International Journal of Managing Projects in Business. https://doi.org/10.1108/IJMPB-01-2019-0020

Published
2023-01-31
Section
Articles