The Analysis Performance of Project Delays in Pile Foundation Work : A Case Study Batam Island

Main Article Content

Steven Shui
Andri Irfan Rifai
Mulia Pamadi

Abstract

Purpose: Delays are common in construction projects. The term "project delay" refers to a project's completion date later than anticipated. Lack of performance by contractors or project managers in resolving issues can result in project delays. The factors that cause project delays must be considered to reduce delays. This study aims to examine the elements contributing to Batam island’s pile foundation construction delays.


Findings: The factor of delays is an important key of the analysis to prevent delays in future projects


Design/methodology/approach: This research uses a case study at Batam Island. The analysis is done with SPSS 26 program.


Research limitations/implications: Analysis of delay caused by pile foundation in Batam island.


Practical implications: Analysis of the delay caused by a project according to the result of the questionnaire.


Originality/value: Original Paper


Paper type: A Case Study

Downloads

Download data is not yet available.

Article Details

Section
Articles

References

Al-Jaf, H. A., & Saeed, Y. S. (2020). Factors of delay in public construction projects in the Kurdistan region of Iraq. Journal of Duhok University, 13.
Alaghbari, W., S., S. R., Alaswadi, W., & Sultan, B. (2018). Delay factors impacting construction projects in Sana’a-Yemen. PM World Journal, 28.
B, F. (2020). The impact of entrepreneurial passion on psychology and behavior of entrepreneurs. Frontiers in Psychology, 11, 1733.
Bekr, G. A. (2018). Study and assessment of causes and effects of delay in large public construction projects in Jordan. Research. International Journal of Applied Engineering, 8(13), 6204-6210.
Byun, Y., & Sohn, B. S. (2020). ABGS: A system for the automatic generation of building information models from two-dimensional CAD drawings. Sustainability, 12(17), 6713.
Candra, C. Y., Hapsari, R., & Sari, E. P. (2021). Analisis Perbandingan Efisiensi Alat Pancang Diesel Hammer Dan Drop Hammer Pada Pekerjaan Pondasi Tiang Pancang Di Lahan Basah. Jurnal Infrastruktur, 2(7), 87–92.
Deep, S., Gajendran, T., & Jefferies, M. (2021). A systematic review of ‘enablers of collaboration’among the participants in construction projects. International Journal of Construction Management, 14.
Hassan, A. K., Adeleke, A. Q., & Taofeeq, D. M. (2019). The effects of project triple constraint on Malaysia Building Projects. Social Science and Humanities Journal, 17.
Henindia, R., & Suroso, A. (2022). Analysis of the Factors Causing Delay in Pile Foundation Work for Medium-Story Building Project. Journal of Applied Science, Engineering, Technology, and Education, 4(1), 27–38.
Institute, P. M. (2017). A guide to the Project Management Body of Knowledge (PMBOK guide) (6th ed.).
Kumar, M., Bardhan, A., Samui, P., Hu, J. W., & Kaloop, M. R. (2021). Reliability analysis of pile foundation using soft computing techniques: a comparative study. Processes, 9(3), 486.
Lee, Y. X., & Ling, F. N. (2022). A Comparative Study On Pile Design Of Residential Buildings On Soft Soil Utilizing End-Bearing Pile Vs. Friction Pile. Recent Trends in Civil Engineering and Built Environment, 3(1), 198-208.
Magar, J., Kudtarkar, A., Pachpohe, J., & Nagargoje, P. (2020). Study and analysis of types of foundation and design construction. IRJET, 7, 3301-3307.
Mittal, Y. K., Paul, V. K., Rostami, A., Riley, M., & Sawhney, A. (2020). Delay factors in construction of healthcare infrastructure projects: a comparison amongst developing countries. Asian Journal of Civil Engineering, 4(21), 649–661.
Nguyen, P. T., Nguyen, T. A., Cao, T. M., Vo, K. D., Huynh, V. D., Nguyen, Q. L., & Le, L. P. (2018). Construction project quality management using building information modeling 360 field. International Journal of Advanced Computer Science, 6.
Patel, M. K., & Joshi, B. R. (2020). Analytical Study on Factor Causing Delay in Surat Construction Industry. The International Journal of Analytical and Experimental Modal Analysis, 5.
Pazha, H., Muhammad, F. H. Agustina, R. D., & Wiratama, R. (2019). The Identification of Hard Bottom Surface Structure using Correlation of Geoelectrical Resistivity Methods and SPT Data as Preliminary Studies for Laying the Foundation at Passing Cross Sumatera Toll Road, South Lampung Station. IOP Publishing, 1155(1), 012007.
Rachid, Z. T., & Mohammed, B. (2019). Causes of schedule delays in construction projects in Algeria. International Journal of Construction Management, 12.
Ramli, M. Z., Malek, M. A., Hanipah, M. H., Lin, C. L., Sukri, M. M., Zawawi, M. H., & Fuad, N. M. (2018). Study of factors influencing construction delays at rural area in Malaysia. In Journal of Physics, 1049(1), 012017.
Rauzana, A., & Dharma, W. (2022). Causes of delays in construction projects in the Province of Aceh, Indonesia. (17th ed.). PloS one.
Rifai, A. I. (2021). Review of Engineer Professionalism in Construction Project Failure: A Case Toll Road Project in Indonesia. In Proceedings of the International Conference on Industrial Engineering and Operations Management, 479–486.
Rifai, A. I., Hadiwardoyo, S. P., Correia, A. G., & Pereira, P. A. (2016). Genetic Algorithm Applied for Optimization of Pavement Maintenance under Overload Traffic: Case Study Indonesia National Highway. Trans Tech Publications Ltd. Applied Mechanics and Materials, 845, 369–378.
Rifai, A. I., Hadiwardoyo, S. P., Correia, A. G., Pereira, P., & Cortez, P. (2015). The data mining applied for the prediction of highway roughness due to overloaded trucks. International Journal of Technology, 6(5), 751-761.
Rizkifani, S. P. (2021). The Validity and Reliability Test of The St George’s Respiratory Questionnaire (SGRQ) Indonesian Version in ARI Patients in The City of Pontianak. Journal of Science, Techology, and Engineering, 1(2), 67–72.
Sari, O. L., Saputra, A. A., Subhakti, A., Putri, A. P., & Khala, C. C. (2021). Impacts Due to Foundation Piling Work. In Journal of Physics: Conference Series, 1726(1), 012018.
Susanti. (2020). Cost overrun and time delay of construction project in Indonesia. (8th ed.). IOP Publishing.
Wang, T. K., Ford, D. N., Chong, H. Y., & Zhang, W. (2018). Causes of delays in the construction phase of Chinese building projects. Engineering, Construction and Architectural Management.
Wuala, H. D., & Rarasati, A. D. (2020). Causes of delays in construction project for developing Southeast Asia countries. IOP Publishing.
Y, R. (2020). Analysis of delay factors and their effects on construction projects. Management Science Letters, 8.