Study of The Impact of design on construction Project Delays

  • Arkiyansyah Arkiyansyah Civil Engineering Doctoral Study, Faculty of Engineering, Tarumanagara University, Jakarta
  • Manlian Ronald A. Simanjuntak Professor of Project Management University of Tujuh belas Agustus 1945 Jakarta
  • Basuki Anondho Faculty of Engineering, Tarumanagara University, Jakarta
Keywords: Project Design, Project Delays, Project Management, Literature Review, Design Planning

Abstract

Project delays are a problem that often occurs in various types of projects, especially construction projects, and have a significant impact on increasing costs, decreasing quality, and stakeholder dissatisfaction. One factor that often contributes to project delays is the design aspect, whether related to completeness, quality, or design changes during the implementation stage. This research aims to comprehensively examine the role of design in project delays based on findings in the scientific literature. The method used is a literature review by examining relevant national and international journal articles, published within the last ten years, and obtained through reputable scientific databases. The study process was carried out through the stages of identification, selection and literature analysis to group design factors that contributed to project delays. The results of the study show that project delays are largely influenced by design problems such as incomplete planning documents, design errors, weak design coordination between disciplines, and design changes that occur during the construction stage. These factors have implications for rework, work flow disruptions, and adjustments to project schedules. The conclusion of this research confirms that design has a strategic role in determining project time performance, so that improving the quality of the planning process and design coordination from the early stages of the project is key in minimizing the risk of delays.

 

Downloads

Download data is not yet available.

References

Amoatey, C. T., & Ankrah, N. A. (2017). Exploring critical road project delay factors in Ghana. Engineering, Construction and Architectural Management, 24(2), 243–259. https://doi.org/10.1108/ECAM-03-2016-0061

Arain, F. M., & Pheng, L. S. (2017). Critical factors affecting the success of construction projects in developing countries. Construction Management and Economics, 35(6), 375–394. https://doi.org/10.1080/01446193.2016.1230052

Doloi, H. (2016). Cost overruns and failure in project management: Understanding the roles of key stakeholders in construction projects. International Journal of Project Management, 34(3), 367–379. https://doi.org/10.1016/j.ijproman.2016.01.001

Enshassi, A., Mohamed, S., Abu Mustafa, Z., & Mayer, P. E. (2018). Factors affecting labour productivity in building projects in the Gaza Strip. Journal of Civil Engineering and Management, 24(5), 395–404. https://doi.org/10.3846/jcem.2018.6138

Gamil, Y., & Rahman, I. A. (2017). Identification of causes and effects of poor communication in construction industry: A theoretical review. Journal of Building Engineering, 12, 85–94. https://doi.org/10.1016/j.jobe.2017.04.002

Gündüz, M., & Almuajebh, M. (2020). Critical success factors for sustainable construction project management. Engineering, Construction and Architectural Management, 27(9), 2385–2405. https://doi.org/10.1108/ECAM-10-2018-0460

Hwang, B.-G., Zhao, X., & Ng, S. Y. (2016). Identifying the critical factors affecting schedule performance of public housing projects. Engineering, Construction and Architectural Management, 23(3), 279–295. https://doi.org/10.1108/ECAM-01-2015-0012

Ikhsan, I., Arifuddin, R., & Abdurrahman, M. A. (2025). Risk analysis of delay in construction project based on design and build contract. Construction Technologies and Architecture, 16, 45–54. https://doi.org/10.4028/p-GKP9mr

Khahro, S. H., Ali, T. H., & Memon, N. A. (2023). Key factors influencing delays in sustainable building construction projects. Sustainability, 15(7), 5872. https://doi.org/10.3390/su15075872

Marzouk, M., & El-Rasas, T. (2016). Analyzing delay causes in Egyptian construction projects. HBRC Journal, 12(3), 271–278. https://doi.org/10.1016/j.hbrcj.2014.03.003

Memon, A. H., Memon, A. Q., Khahro, S. H., & Javed, Y. (2023). Investigation of project delays: Towards a sustainable construction industry. Sustainability, 15(2), 1457. https://doi.org/10.3390/su15021457

Sambasivan, M., Deepak, T. J., Salim, A. N., & Ponniah, V. (2017). Analysis of delays in construction industry and mitigation measures. Built Environment Project and Asset Management, 7(2), 128–144. https://doi.org/10.1108/BEPAM-10-2016-0044

Sanni-Anibire, M. O., Mahmoud, A. S., & Hassanain, M. A. (2020). Causes of delay in construction projects in developing countries. Journal of Engineering, Design and Technology, 18(2), 263–281. https://doi.org/10.1108/JEDT-04-2019-0098

Shoar, S., & Chileshe, N. (2021). Exploring the causes of design changes in building construction projects: An interpretive structural modeling approach. Sustainability, 13(17), 9578. https://doi.org/10.3390/su13179578

Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2019). Delays in construction projects: The case of Jordan. International Journal of Construction Management, 19(5), 375–384. https://doi.org/10.1080/15623599.2018.1484859

Vahedi Nikbakht, M., Gheibi, M., Montazeri, H., Yeganeh Khaksar, R., Moezzi, R., & Vadiee, A. (2024). Identification and ranking of factors affecting the delay risk of high-rise construction projects using AHP and VIKOR methods. Infrastructures, 9(2), 24. https://doi.org/10.3390/infrastructures9020024

Yap, J. B. H., Goay, P. L., Woon, Y. B., & Skitmore, M. (2021). Revisiting critical delay factors in building construction projects. Alexandria Engineering Journal, 60(1), 171–185. https://doi.org/10.1016/j.aej.2020.11.021

Yusoff, S. S. F. M., & Ismail, Z. (2024). Delays in interior design construction contract: A literature review. International Journal of Innovation and Industrial Revolution, 6(19). https://doi.org/10.35631/IJIREV.619003