Development of Risk Governance and Logistics Framework for Government Building Projects in 3T Areas
Abstract
The construction of government buildings in the Southwest Papua region faces different challenges compared to construction projects in urban areas of Indonesia. The characteristics of the archipelago, limited transportation infrastructure, high dependence on material distribution from outside the region, and socio-cultural complexity of local communities cause a high risk of project delays. This research aims to develop a risk management and logistics framework that is in accordance with the characteristics of government building construction projects in the Southwest Papua region. The research uses a qualitative case study approach with research locations on several government building projects implemented in Raja Ampat Regency, Sorong Regency, and Sorong City. The informants consist of contractors, supervisory consultants, commitment makers, project managers, and community leaders selected through purposive sampling. Data were collected through in-depth interviews, field observations, and documentation studies. Data analysis was carried out using the interactive model Miles, Huberman, and Saldaña through the process of data reduction, data presentation, and conclusion drawn. The results of the study show that project delays are influenced by five main themes, namely geographical and logistical barriers, socio-cultural dynamics of local communities, weak coordination between stakeholders, limited project risk management capacity, and uncertainty in the procurement of construction materials. The research resulted in an archipelagic region-based integrated risk governance and logistics framework that emphasizes risk identification from the planning stage, strengthening multi-stakeholder coordination, logistics buffer strategies, and local community involvement. These findings make a theoretical contribution to the development of 3T regional construction project risk management as well as practical implications for local governments and construction implementers.
Downloads
References
Enderzon, V. Y., & Soekiman, A. (2020). Manajemen Risiko Proyek Konstruksi Flyover di Indonesia dengan Metode House of Risk (HOR). Media Teknik Sipil, 18(1), 57–68.
Harita, H. (2024). Strategi Pengelolaan Risiko dalam Konstruksi. IDENTIK: Jurnal Ilmu Ekonomi, Pendidikan dan Teknik, 1(2), 1–10.
Kelo, R. F., et al. (2025). Analisis Pengelolaan Proyek Konstruksi Berbasis Manajemen Risiko. Jurnal Maroso, 8(1), 45–58.
Miles, M. B., Huberman, A. M., & Saldaña, J. (2020). Qualitative Data Analysis: A Methods Sourcebook (4th ed.). Sage.
Norken, I. N. (2015). Pengantar Analisis dan Manajemen Risiko pada Proyek Konstruksi. Udayana University Press.
Patrickson, S., et al. (2024). Manajemen Risiko pada Proyek Pembangunan Infrastruktur Strategis. Jurnal Teknik Sipil, 31(2), 120–135.
Pratin, D. S., et al. (2024). Risiko-Risiko Dominan Pengadaan Pekerjaan Konstruksi Pemerintah. Jurnal Inovasi Pembangunan, 12(1), 33–48.
Setiawan, M. A., & Karyasa, I. K. (2021). Penerapan Manajemen Risiko pada Proyek Konstruksi Gedung. Media Teknik Sipil, 19(2), 87–99.
Tinambunan, Y. (2024). Manajemen Risiko dalam Proyek Konstruksi: Evaluasi dan Implementasi. Jurnal Ekonomi dan Manajemen Infrastruktur, 5(1), 21–35.
Abas, M., Khattak, S. B., Habib, T., & Nadir, U. (2022). Assessment of critical risk and success factors in construction supply chain: A case of Pakistan. International Journal of Construction Management, 22(12), 2258–2266. https://doi.org/10.1080/15623599.2020.1783597
Alawneh, Rami, Jannoud, Ismael, Rabayah, Hesham, Asaad, Samaher, Almasaeid, Hatem, Imam, Rana, & Ghazali, Farid Ezanee Mohamed. (2024). Development of a new method for assessing project risks in sustainable building construction projects in developing countries: The case of Jordan. Buildings, 14(6), 1573. https://doi.org/10.3390/buildings14061573
Albasyouni, Wahbi, Kamara, John, & Heidrich, Oliver. (2025). Key challenges and opportunities to improve risk assessments in the construction industry. Buildings, 15(11), 1832. https://doi.org/10.3390/buildings15111832
Almashhour, Raghad, Al-Mhdawi, M. K. S., Daghfous, Abdelkader, Qazi, Abroon, & Ojiako, Udechukwu. (2025). Traditional to sustainable risk management in the construction industry: A systematic literature review. International Journal of Managing Projects in Business. https://doi.org/10.1108/IJMPB-01-2025-0021
Badkoubeh, Mohammad, Ghannadpour, Seyed Farid, & Noori, Siamak. (2024). Designing a construction supply chain model using backup suppliers under disruption risks. Journal of Civil Engineering and Management. https://doi.org/10.3846/jcem.2024.21450
Chen, Shicheng, Eyers, Daniel R., Gosling, Jonathan, & Huang, Ying. (2025). Supply chain risks for SMEs in construction projects: A structured literature review and research agenda. The International Journal of Logistics Management. https://doi.org/10.1108/IJLM-12-2023-0548
Ichsan, Muhammad. (2024). Development of a risk-based strategy for construction projects in Indonesia. Cogent Engineering. https://doi.org/10.1080/23311916.2024.2307212
John, Nsikan, Nwaguru, Patrick, & Williams, Anthony J. (2024). Managing materials vendor risks for improved project quality in construction supply chains. Brazilian Journal of Operations & Production Management. https://doi.org/10.14488/BJOPM.1957.2024
Lubis, Ahmad M. (2023). Risk mitigation in supply chain disruption during construction projects in Indonesia. Jurnal Ekonomi. https://ejournal.seaninstitute.or.id/index.php/Ekonomi/article/view/3183
Muhammad, Firdaus Yusri. (2025). Design of project risk management to mitigate construction project delays. Journal of Business and Technology. https://bustechno.polteksci.ac.id/index.php/jbt/article/view/518
Parisi, Leonardo. (2025). Advancing materials procurement processes in construction. International Journal of Construction Management. https://doi.org/10.1080/15623599.2025.2553610
Wepari, Joseph W. (2024). Mitigating the effects of delay risk in building construction projects. Cogent Engineering, 11(1). https://doi.org/10.1080/23311916.2024.2345522
Winata, Leo E. (2024). The effects of governance on performance: The case of public–private partnership toll roads in Indonesia. International Journal of Construction Management. https://doi.org/10.1080/15623599.2023.2219937
Yun Zhen, G. W. (2025). Application of building information modelling in addressing delay issues in high-rise building projects. International Journal of Construction Management. https://doi.org/10.1080/15623599.2025.2522230
Zagia, F. (2025). Prioritizing the key causes of construction project delay in building projects. International Journal of Construction Management. https://doi.org/10.1080/15623599.2025.2568103
Copyright (c) 2026 IJEBD (International Journal of Entrepreneurship and Business Development)

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.